Completion of the construction of 11 affordable homes (a mix of two, three and four-bedroom units), including all associated external works and infrastructure, for Sandwell Council. The works were undertaken following the insolvency of the original contractor.
Client
Location
Contract Sum
Programme
27 Weeks
Completion of the construction of 11 affordable homes (a mix of two, three and four-bedroom units), including all associated external works and infrastructure, for Sandwell Council. The works were undertaken following the insolvency of the original contractor.
The project is being delivered under a JCT 2016 Traditional Contract With Quantities. The scheme remains live on site, with a scheduled completion date of May 31, 2025.
At the time of possession, the site was in a partially completed state, with 9 of the 11 plots at various stages of oversite. Due to a 9-month period of inactivity, several of these oversites had deteriorated and required remedial works prior to progressing with construction.
The scheme utilises a traditional form of construction, consistent with the initial design intent and incorporates sustainable technologies, including- Solar Photovoltaic (PV) panels, aligning with the council’s environmental and energy-efficiency objectives.
The Project team;
Contract Administrator – Sandwell Council
Architect – Sandwell Council
Civil Engineer – Sandwell Council
Structural Engineer – AJP
Building Control – LABC
Structural Warranty – Advantage